Golgohar Fourth Line Concentrate Complementary Plant

Client : Golgohar Mineral & Industrial co

Place : Sirjan, Kerman, Iran

Capacity : 3 MTPA, Crushing, Sizing, Handling, Stacking and Feed and 2MTPY Handling and Loading of Concentrate

Summary of the project: Crushing, Reclaiming of Feed, Stacking and Reclaiming of

 Iron Ore Concentration, Automatic Truck Loading of Concentrate, Tailing Dewatering 

Duration of Contract : 18 months

Project Status :Final Acceptance Certificate

Contract  Type :  EPC